Migratetogw8project
From CoolSolutionsWiki
mccarran migrate to GW 8 project
Contents |
[edit]
high-level layout
- Current high level server requirements
- physical gw1: DOA po,gwia, mta, edir
- physical gw2: DOA bectel
- physical reload - diff. core room
- physical edir2
- VM1: webaccess, im
- VM2: edir2 replication
- VM3: edir and gwmon
[edit]
schedule
- Oct 10th test/verify reload after hours
- Oct 16th migrate during production hours
[edit]
task list
- X Obtain OES 2 activation code and ensure automatic updates through the channel works. If NSS is not used, only charge for eDir license
- X Once activation codes for sles 10 and oes 2 are working, update box to all new patches
- X setup slpda for vmedir1
- X configure as DA
- X configure all servers to point to vmedir1 as their slpda
- X configure nwc1 and nwc2, app2 and nwmaster to not respond to icmp pings...so NW clients think they are invisible and won't authenticate to them.
- X Once updates is working, add edir replica to vmedir1
- Ensure 3 replicas per partition, then retire nw 6.0 servers that are no longer used.
- Connect gwmail3 to SAN
- Ensure disk performance is acceptable for GW
- Perform pre-migration health check
- Install and configure GW 8. Migrate Primary domain to Mail3 and upgrade it to gw8
- Create new GW 8 post office and pilot users (migrate select staff)
- Once pilot is successful, migrate other agents and their databases to gwmail 3
- While monitoring large PO move, build out and configure Vmwares for edir/gwmon
- Install and configure RELOAD
- verify reload
- archive - stored on file share user1
- can you open gw 7 archives with gw 8?
- move and upgrade Primary
- validation test a few IT users on a new GW 8 PO
- verify archive
- gw 8 caching
- validation test a few IT users on a new GW 8 PO
- migrate bectel PO off old hardware to gwmail1 (after monitoring period and after gwmail1 is rebuilt to oes 2 sp2) -- ## verify reload works, including migrate back - in preparation for migrating large PO to GW 8 server.
- install new webaccess to VM machine once all Post offices are on GW 8
- migrate GWIM to VM
- Perform post migration to gw 8 health check
[edit]
Thomas todo
- X multi outgoing smtp
- sent my lab notes of how I did this
- dib script
- can you open gw 7 archives with gw 8?
- yes
- get reload experience a 2 min outage on migration? how should we test/verify.